ARTICLE COMPANION

Reporting-system acceptance sheet

Static discussion worksheet for a reporting analyst, planner and authorised review owner. Proposed for local use; not operationally trialled. Use approved organisational storage for real records. No upload service, automation, scoring or integration is supplied.

Inputs: decision and authority, source references and coverage, definition, representative records, hand count, exceptions, user-task observations and acceptance evidence. Outputs: an agreed test record, visible unresolved issues and a named decision about whether the report is suitable for the stated use. Assumes access to applicable source history and people able to verify it. Does not establish physical readiness, safe execution or causes of delay. A signature records a person's acceptance, not automatic certification.

Fictional completed example

Decision: identify overdue Northbank corrective orders needing preparation checks before Thursday's schedule discussion.

Authority: supervisor accepts review actions; scheduling, risk and deferral decisions follow the site's arrangements.

Definition: v1, Sunday 18 October 2026 23:59 site time; Northbank corrective orders, target before 19 October, status Approved / Waiting materials / Ready. Exclude Complete / Cancelled. Missing date is a separate exception.

Sources: fictional 6-order cut-off extract, checked 3-equipment list, 7 status events and WO-1101's supplied delivery note. Target dates assumed verified as applicable at cut-off. Extract coverage is an invented premise.

Expected reconciliation: 6 distinct orders = 4 included + 2 excluded. Included statuses: 2 + 1 + 1 = 4. One unresolved equipment reference remains in the total. Seven history rows must not become 7 orders or 5 overdue orders.

Boundary cases: due 19 October excluded; missing target date flagged; duplicated history event doesn't increase orders; reopened order and late correction require accepted rules.

User task: find WO-1106; explain inclusion and unresolved equipment; identify source owner and next check. No actual user trial performed.

Proposed action: Ellis verifies reference by Tuesday noon; supervisor accepts. Return evidence: accepted equipment reference and correction record. Proposed further action: Mara asks materials for WO-1101's delivery position by Wednesday noon.

Acceptance: illustrative only. No real person has accepted a deployed system.

Blank working sheet

  1. Who uses this, at which review, to support which decision?

Answer:

  1. What may they authorise? Who accepts risk, scheduling or deferral decisions?

Answer:

  1. Definition/version, cut-off/time zone, population, dates, statuses and exceptions:

Answer:

  1. Source owner, extract reference, coverage, applicable history and access permissions:

Answer:

  1. Meaning of one row in each input and prepared table; accepted keys and unresolved links:

Answer:

  1. Hand result and included/excluded order identifiers; reconcile groups to total:

Answer:

  1. Boundary, duplicate, missing-value, reopened-order and late-correction tests with expected results:

Answer:

  1. Reader task observed, actual behaviour, confusion and changes needed:

Answer:

  1. AI task (if any), permitted evidence, output reference, unsupported additions found, reviewer and acceptance:

Answer:

  1. Action/reference, owner, due time, accepting person and expected return evidence:

    Answer:

  2. Failure/stale-data procedure, support owner and previous accepted version:

    Answer:

  3. Accepted for which use, by whom, when, with which limitations? Next review date:

    Answer: