Static discussion aid. Agree rules with the accountable process owner before using a result. Keep actual operational records in approved storage.
Fictional completed example
| Field | Agreed example |
|---|---|
| Decision / owner | Supervisor chooses preparation/scheduling issues to investigate |
| Name / unit | Frozen weekly schedule completion / distinct order count |
| Population / evidence | WO-901–912; Friday 2 October 2026 15:00 frozen list |
| Work period | 5–11 October 2026; Sunday 23:59 end; Europe/London |
| Evidence check | Monday 12 October 08:00; supervisor accepts scope/tests evidence |
| Numerator rule | Entire frozen scope and required tests physically complete by the period end, supported at evidence check; accepted early completion also counts for orders in the frozen list |
| Exclusions | Post-freeze additions excluded from both parts; none removed from frozen selection |
| Cancellation / deferral | Keep denominator; incomplete scope contributes no completion |
| Reopening | Inspect original scope/evidence; WO-909 unfinished required test = no completion |
| Late closure | WO-908 Sunday physical completion accepted despite Monday administrative closure |
| Fraction | 901–907: 7, 908: 1; total 8/12 = 66.7%; 909–912: 4 misses |
| Additional work | WO-913 outside both numerator and denominator; reviewed separately |
| Target / display | >=80% fictional target; compare unrounded; display 1 decimal; zero denominator N/A |
| Responsibilities | Scheduler retains freeze; analyst reconciles; supervisor accepts meaning/evidence |
| Version / correction | Proposed example v1; retain issued result and accepted corrections with reasons; no live approval claimed |
Blank definition for local review
| Question | Proposed answer / evidence reference |
|---|---|
| Which decision, who is accountable, and when will they use it? | |
| What is the name and counting unit? | |
| What population, sites, work types and frozen selection apply? | |
| What is the numerator, and what evidence supports each classification? | |
| What is the denominator? Can all identifiers be reconciled once each? | |
| Which time zone, period, freeze and evidence cut-off apply? | |
| Which date means physical completion? What tests/scope must be finished? | |
| How are additions, cancellations, deferrals and duplicates handled? | |
| How are reopened orders and late administrative closures checked? | |
| What happens to missing evidence and zero denominator? | |
| Target, basis, comparison and rounding rules? | |
| Which complementary records prevent misleading conclusions? | |
| Who retains sources, maintains calculation, and accepts interpretation? | |
| Version, effective date, change authority and correction history? | |
| Test normal, reopened, cancelled and late-closed examples: same result? | |
| Owner acceptance, date and unresolved issues? |
Output: an accepted local definition plus reproducible order reconciliation. Assumptions: checked history and scope are available; decision owner can resolve exceptions. This sheet cannot establish physical completion or authorise maintenance work. A calculator based on it remains a separate proposal.