ARTICLE COMPANION

KPI definition worksheet

Static discussion aid. Agree rules with the accountable process owner before using a result. Keep actual operational records in approved storage.

Fictional completed example

Field Agreed example
Decision / owner Supervisor chooses preparation/scheduling issues to investigate
Name / unit Frozen weekly schedule completion / distinct order count
Population / evidence WO-901–912; Friday 2 October 2026 15:00 frozen list
Work period 5–11 October 2026; Sunday 23:59 end; Europe/London
Evidence check Monday 12 October 08:00; supervisor accepts scope/tests evidence
Numerator rule Entire frozen scope and required tests physically complete by the period end, supported at evidence check; accepted early completion also counts for orders in the frozen list
Exclusions Post-freeze additions excluded from both parts; none removed from frozen selection
Cancellation / deferral Keep denominator; incomplete scope contributes no completion
Reopening Inspect original scope/evidence; WO-909 unfinished required test = no completion
Late closure WO-908 Sunday physical completion accepted despite Monday administrative closure
Fraction 901–907: 7, 908: 1; total 8/12 = 66.7%; 909–912: 4 misses
Additional work WO-913 outside both numerator and denominator; reviewed separately
Target / display >=80% fictional target; compare unrounded; display 1 decimal; zero denominator N/A
Responsibilities Scheduler retains freeze; analyst reconciles; supervisor accepts meaning/evidence
Version / correction Proposed example v1; retain issued result and accepted corrections with reasons; no live approval claimed

Blank definition for local review

Question Proposed answer / evidence reference
Which decision, who is accountable, and when will they use it?
What is the name and counting unit?
What population, sites, work types and frozen selection apply?
What is the numerator, and what evidence supports each classification?
What is the denominator? Can all identifiers be reconciled once each?
Which time zone, period, freeze and evidence cut-off apply?
Which date means physical completion? What tests/scope must be finished?
How are additions, cancellations, deferrals and duplicates handled?
How are reopened orders and late administrative closures checked?
What happens to missing evidence and zero denominator?
Target, basis, comparison and rounding rules?
Which complementary records prevent misleading conclusions?
Who retains sources, maintains calculation, and accepts interpretation?
Version, effective date, change authority and correction history?
Test normal, reopened, cancelled and late-closed examples: same result?
Owner acceptance, date and unresolved issues?

Output: an accepted local definition plus reproducible order reconciliation. Assumptions: checked history and scope are available; decision owner can resolve exceptions. This sheet cannot establish physical completion or authorise maintenance work. A calculator based on it remains a separate proposal.