Static companion draft for owner review. Original MDP worksheet; examples are fictional. No automated checks or integration. Use within approved organisational data arrangements. A completed field doesn't establish the truth of its contents.
Worked example
| Field | Example |
|---|---|
| Decision and accountable owner | Mara accepts a limited trial of the material-confirmation handover before schedule freeze, within her delegated authority |
| Measure and definition version | Count-based weekly schedule attainment, example version 1, effective 5 June 2026 |
| Population | 10 distinct orders frozen at 15:00, Friday 5 June, for 8–14 June 2026 |
| Completion rule | Agreed scope physically complete by Sunday 14 June, 23:59; supervisor checks supporting record |
| Exclusions and changes | Post-freeze additions separate; removed orders stay in original denominator with reason |
| Source and reporting cut-off | Frozen schedule plus checked completion records; evidence checked at 08:00, Monday 15 June |
| Reconciliation and target | 6 complete + 4 misses = 10; 6/10 = 60%; fictional target ≥80% |
| Source exception | WO-6207; pre-freeze note requests variant check; materials coordinator confirms wrong reserved coupling |
| Uncertainty | Why the unresolved identity check passed schedule agreement remains to be investigated |
| Agreed action | Trial checked material evidence on material-dependent candidate jobs before next freeze |
| Action owners and dates | Iona: list by 18 June. Sam: evidence by 19 June, 10:00. Scheduler: use evidence at 15:00 freeze |
| Acceptance and review | Mara checks process commitments on 22 June; checked list, exceptions and schedule decisions required. Outcome reviewed separately on 29 June |
| Follow-up observations | 5 candidates checked before 19 June freeze: 4 accepted, 1 held with follow-up owner. New schedule covers 22–28 June; completion cut-off 28 June, 23:59; evidence checked 29 June, 08:00: 8/10 = 80% |
| Limits on interpretation | The 8–14 June result stays 60%; 15–21 June isn't shown. Comparing 8–14 with 22–28 June doesn't establish causal effect. Waiting work remains visible |
| AI use and human check | Proposed draft summarises supplied records only. Planner checks notes; materials confirms identity; Mara accepts action. Retain draft/corrections when testing |
Blank copy
| Field | Your review |
|---|---|
| Decision needed; decision owner and authority | |
| Measure; definition version and effective date | |
| Population; frozen selection or selection rule | |
| Period; event dates; reporting/extract cut-off | |
| Completion/classification rule | |
| Exclusions; additions; removals; corrections | |
| Calculation; target and basis | |
| Source references; record grain; reconciliation | |
| Exception/order; supplied observations | |
| Missing evidence; person who can confirm it | |
| Possible explanation; evidence needed to test it | |
| Human decision; accepted by; date | |
| Action; owner; due date; required support | |
| Acceptance evidence; next review date | |
| What happened; effect; other changes to consider | |
| Waiting work or unintended consequence | |
| Feedback to collector; next change | |
| AI inputs/draft; human corrections and acceptance |
Start with one exception. Retain the original result and identify any later correction. Physical readiness, technical findings and operating decisions require their normal competent checks and authority.